Jasper Propane Conversion

Electrical scope & backup power

Backup heat: the load that decides your electrical scope

Electric resistance strip heat is the supplemental stage in a straight heat pump conversion. It runs when outdoor temperature falls below the balance point, during defrost cycles, and if the compressor fails.

Free and no obligation. You are connected to one independent, licensed, insured Georgia contractor serving your area — never a call center, never a list.

An electric strip heat kit installed in an air handler with its factory breaker block, the largest single load in a converted mountain home
Propane pre-buy season: August 15 to November 30 2026. Suppliers are issuing winter lock-in quotes now — 59 days left to price the conversion before you commit gallons. A conversion completed in autumn runs on electricity for the whole season, and lead times lengthen sharply once the first cold snap arrives. Compare your contract options.

Electric strip heat is sized to the shortfall between heat pump capacity at design temperature and the house's heat loss, not to the whole heating load. Banks come in 5, 10, 15 and 20 kW, drawing roughly 21, 42, 63 and 83 amps at 240 volts, treated as continuous load at 125% for conductor and breaker sizing.

How strip heat is circuited

Strip heaters are resistance elements installed in the air handler, typically supplied in banks of 5, 10, 15 or 20 kW. Each bank draws substantial current at 240 volts, and the code requirements follow directly:

  • Fed by two-pole breakers, because the load is 240V.
  • Treated as a continuous load, so overcurrent protection and conductors are sized at 125% of the calculated current.
  • Frequently split across multiple circuits — manufacturers commonly limit a single circuit to 48 amps, so larger banks arrive as multiple sub-circuits with individual protection.
  • Conductors sized to the ampacity required after the continuous-load factor, with correction for ambient temperature where the run passes through a hot attic.
  • Terminated at the air handler's factory-supplied breaker kit where one is provided — field-fabricated arrangements are a common inspection failure.
Conductor terminations and staging sequencer inside an air handler, the controls that keep resistance backup heat from running unnecessarily

Sizing: less is usually the correct answer

Strip heat should be sized to the shortfall between the heat pump's delivered capacity at design temperature and the house's calculated heat loss — not to the whole heating load, which is how it is habitually specified.

The default of fitting the largest bank the air handler accepts is defensive rather than engineered, and it costs twice: once in the electrical scope required to feed it, and again every winter it runs instead of the heat pump.

ApproachConsequence
Sized to full heating loadLargest bank, most circuits, service upgrade near-certain, highest winter operating cost.
Sized to calculated shortfall at design tempSmaller bank, often fewer circuits, service upgrade frequently avoided, strips engage rarely.
Dual-fuel — no strips at allPropane furnace is the backup stage. Largest load removed from the calculation entirely. See dual-fuel.

Want this run against your own delivery ticket and EMC bill? It takes one call. Free, no obligation.

Call (470) 208-3151

Sequencers, lockouts and staging

Strip heat should never simply switch on with the compressor. Correct control is what keeps it from dominating your winter bill:

  1. Sequencers bring elements on in stages with a delay between them, limiting inrush and avoiding all-or-nothing operation.
  2. Outdoor lockout prevents the strips engaging above a set outdoor temperature, so they cannot run on a mild day because the thermostat was nudged up.
  3. Staged supplemental control allows the thermostat to call for only the elements needed rather than the full bank.
  4. Defrost-only operation uses a minimal element during defrost cycles to temper supply air, without engaging the full bank.

A system where the thermostat's 'Emergency Heat' setting bypasses the compressor entirely should be understood by the homeowner as a failure mode, not a comfort setting. It runs the house entirely on resistance heat at a COP of 1.0, and left on by accident for a month it produces the electricity bill that makes people distrust heat pumps.

What to verify at commissioning

  • Breaker sizes match the nameplate and the installed elements, not the air handler's maximum rating.
  • Conductor sizes match the breakers, with derating applied for attic or high-ambient routing.
  • Outdoor lockout is configured to a temperature that reflects your actual balance point — not left at a factory default.
  • Staging operates: verify each stage engages independently.
  • The homeowner has been shown what 'Emergency Heat' does and when to use it, which is essentially only when the compressor has failed.

Run your own numbers

Delivered-BTU math, not a marketing estimate. Change any input and the result updates.

$1,768less per winter on electric

Example only: a house burning 850 gallons at $3.20/gal through an 80% furnace, against electricity at $0.13/kWh. Backup strip heat in a hard cold snap is not modeled. Enter your own numbers above.

Delivered heat needed
62.2 million BTU
Propane cost per delivered MMBTU
$43.71
Heat pump cost per delivered MMBTU
$15.29
Electricity used
7,320 kWh
This winter on propane
$2,720
This winter on a heat pump
$952

Worked example at typical North Georgia prices. Change any input above and this recalculates for your house. Estimate only, not a guarantee.

Free and no obligation. You are connected to one independent, licensed, insured Georgia contractor serving your area — never a call center, never a list.

Common questions about strip heat circuits & breakers

How much strip heat do I need?

Only enough to cover the gap between what the heat pump delivers at design temperature and what the house loses. On a correctly specified cold-climate system in Pickens County that gap is small, and the bank is correspondingly small. The Manual J and the equipment's extended capacity table produce the number together.

Why is my electric bill enormous when emergency heat is on?

Resistance heat converts electricity to heat at a COP of 1.0, while the heat pump delivers roughly two and a half to four times as much heat per unit of electricity. Running on strips means paying two to four times as much per BTU. If your bill spiked, check whether the thermostat was left on Emergency Heat.

Can I add strip heat later if I need it?

Sometimes, if the air handler has capacity for an additional bank and the electrical service supports the added load. It is far cheaper to size it correctly during the conversion than to return afterwards and possibly trigger a service upgrade at that point.

Where these numbers come from

Every contractor in this network holds a current Georgia Conditioned Air or Electrical Contractor license. You can confirm any license yourself before you sign anything — Georgia Secretary of State license lookup.

Get a conversion figure for your address

Ask what balance point our proposal produces and what strip bank follows from it. Those two numbers set your electrical cost.

Call (470) 208-3151 or send the details and we will call you back

Free and no obligation. You are connected to one independent, licensed, insured Georgia contractor serving your area — never a call center, never a list.

No obligation and no cost. Consumer education and contractor referral network. All mechanical work is performed by independent, licensed, insured Georgia contractors. We pass your details to one contractor serving your area — not to a call center, and not to a list.

Call (470) 208-3151Get my figures